Wet Weather Delays: How to Protect Your Project Schedule

Wet Weather Delays: How to Protect Your Project Schedule

0:00|0:00

Wet weather can derail outdoor project schedules and budgets—but clear allowances, timely client updates, and consistent records can help support extension and cost claims. Michael explains how to set monthly rain-day allowances, report days allowed, used, and remaining, and prepare for lingering impacts such as waterlogged ground and damaged equipment.

https://myprojectlessons.com/wet-weather-delays/


Chapter 1

x

Michael

G'day, and welcome to My Project Management Lessons. I'm Michael, and today we're talking about wet weather delays. Picture a trip you've planned right down to the minute. Tickets booked, connections mapped out, home in time for dinner. Then the weather rolls in, the flight's grounded, the train goes nowhere, and you're stuck hitching a ride in whatever vehicle'll take you. Suddenly a quick trip turns into an epic odyssey. If you've ever watched a classic eighties comedy about exactly that, you'll know the feeling. Well, an outdoor project can go the same way.

Michael

Here's the thing. It's rare for an outdoor project not to be affected by wet weather. If you manage one, schedule changes from rain are something you'll have to deal with. You can't stop the rain, mate, but you can plan for it.

Michael

So let's start with the problem. Wet weather can seriously hurt the delivery schedule, and the costs that go with it, on any job that includes outdoor work or depends on it. But many clients are reluctant to extend the schedule or approve extra costs because of rain. They'll often say, well, it's a bit of rain, what did you expect?

Michael

And honestly, that's not a crazy thing to say, if you haven't planned for it. A study in the UK showed project durations get extended by an average of 21 percent because of the weather. Twenty one percent. That's not a rounding error. It's a big detour on the map.

Michael

So here's the solution. Allow for wet weather in your schedule, and report on it. Most clients will only grant extra time or money if the wet weather meets certain criteria. Usually that's based on recorded rainfall in the area, either from official sources or from a rain gauge on your site, going over a set number of days for that month. For example, a contract might say you should allow five days of wet weather each month, and you only get a variation if the recorded rain days go over that number.

Michael

Now, what if the contract doesn't say anything? Then you go and get the official local government average rain days for the area. Here in Australia, that means the Bureau of Meteorology and their rainfall maps. You put that allowance into your offer, and you state the number of rain days you've allowed for each month. Clear as a bell.

Michael

Once the allowance is in your schedule, it's much easier to get an extension of time or cost claim approved. And when the weather does turn up, keep clear records of it. Tell the client early that the weather might delay the schedule. If it actually does hit your program, let them know as soon as possible, and tell them you'll be making an extension of time claim, and possibly a cost claim, as per the contract. Use a formal claim form too. Your client's form is best, but if they haven't got one, use your own template. My post points to one on Sitemate as an example.

Michael

Then in your monthly reports, list three numbers: wet weather days allowed, days used, and days remaining. That way, when you apply for an extension, the evidence is already sitting there, report after report. No scrambling, no digging through old emails.

Michael

And if you're on the client side, same deal. Make the allowances in your own schedule, and ideally state the wet weather day allowances in the tender or offer request and in the contract. A clearly written section means both sides know what rain does to the job.

Michael

One more thing, and it's a sneaky one. The delay doesn't end when the rain stops. The ground might be too wet for excavation until it dries out. Flooding might've moved materials or damaged equipment. Lightning or wind might've damaged or destroyed gear, and replacing it costs time and money. It's like when the storm's passed and you think you're finally rolling again, and then the next leg of the journey falls over.

Michael

So put measures in place. Extra drainage. Don't put laydown areas at a low point. Keep pumps ready to shift water off the site. And schedule work for the dry periods, not the rainy season. My blog post also points to a great piece from Paul Netscher on avoiding weather related project delays, so have a look at that.

Michael

Do all that, keep your client informed, and you've got solid reasons and evidence for delays without penalty. Just make sure your contract actually allows for it. So the lesson is simple. Allow for wet weather delays, show them clearly in your schedule, and report on them regularly.

Michael

Your action step this week: check your contract or your baseline schedule and see if there's a set number of rain days for each month. If there isn't, grab the local average from the Bureau of Meteorology (or your local equivalent) and add it. Then add an allowed, used and remaining column to your monthly report. Easy.

Michael

If you want more, there are related posts on My Project Management Lessons: Notify Your Client of Project Delays, Document Design Changes and Delays, and Evidence for Late Completion. You'll find the full details at My Project Lessons dot com. Thanks heaps for listening, and I hope your next journey runs on time, rain or shine. See ya!